8000 from plant A with 1% defective
x from plant B with 4% defective
8000 + x = y with 3% defective
da/a = 0.01 -> 80 = da
db/b = 0.04 -> db = 0.04b
(da+db)/(a+b) = 0.03
(80+b0.04)/(8000+b) = 0.03
80+b0.04 = 0.03(8000+b)
80+b0.04 = 240 + 0.03b
80 - 240 = 0.03b - b*0.04
-160 = -0.01b
b = 160/0.01
b = 16000
the panels from the plant b were 16000