It takes 4000 persons hours to complete a project. How many weeks will it take a team of 5 people to complete the project if each person works 8 hours a day, 5 days a week?

Verified Answer :

Etrade Etrade
  • 02-05-2016

4000/5 people = 800 hours per person.
5x8 = 40 hours a week per person
40x5 people = 200 hours a week with all 5 people working.
800/200 = 4 weeks
The answer is 4 weeks

Answer Link

Related Questions

People who believe man developed from a lower form of life are called evolutionists monogamists monotheists polytheists
Guys please suggest a new business service or product Remember its new and does not exist Thanks
Makeshift cities during the Great Depression were called shanty towns depressing dwellings Hoovervilles poor man ghettos
What is price discrimination
what is the scale factor of triangle rst to triangle UVW where rst and uvw both have side Lengths 877
Which of the following likely formed Mars moons
quote from the scenario four challenges faced by the music industry
The first step in digestion starts with tongue esophagus saliva
Which part of the female reproductive system provides the opening for sperm to enter the body and babies to exit the body
which of the following is not a way to gather information for a problemandsolution essay A conduct interviews B use an outline C distribute a survey D cite exam